Bridge #56 - 266th St. over Taylor Creek

Project Information

Current Status

9/13/23: Preliminary design is underway.

Project Location

Bridge 56 carries 266th St. over Taylor Creek. 

Google_StreetView Opens in new window


Reason for Project

The bridge deck and beams are deteriorated. A superstructure replacement is recommended.

Project Scope

Bridge Rehabilitation – The bridge deck and beams will be replaced.

Construction Details

  • Design Firm: GAI
  • Inspection Firm: TBD
  • Contractor: TBD
  • Construction Start Date: Spring 2025
  • Construction Completion: Summer 2025
  • Construction Cost: TBD

Funding

Design and construction costs will be funded locally.