Bridge #56 - 266th St. over Taylor Creek

Project Information


Current Status


8/30/21: Project Scoping report completed.

Project Location


Bridge 56 carries 266th St. over Taylor Creek. 
Google_StreetView

Reason for Project

The bridge deck and beams are deteriorated. A superstructure replacement is recommended.



Project Scope


Bridge Rehabilitation – The bridge deck and beams will be replaced.

Construction Details


  • Design Firm: GAI
  • Inspection Firm: TBD
  • Contractor: TBD
  • Construction Start Date: Spring 2025
  • Construction Completion: Summer 2025
  • Construction Cost: TBD
Funding
Design and construction costs will be funded locally.