Bridge #72 - 266th St. over Cicero Creek

Project Information


Current Status


4/27/22: Construction will begin in the spring.

Please be advised, beginning on or after Monday, May 2, 2022, 266th Street between Mt. Pleasant Road and Startsman Road will be closed to all thru traffic for the rehabilitation of Bridge No. 72. The anticipated roadway opening date is Friday, September 30, 2022.

Local traffic will continue to have access to their homes, while thru traffic is asked to utilize the posted detour route of Mt. Pleasant Road, E. 256th Street, and Rulon Road.

Project Location


Bridge 72 carries 266th St. over Cicero Creek. 
Google_StreetView

Reason for Project

The bridge deck is experiencing deterioration and replacement is recommended.



Project Scope


Bridge Rehabilitation – The bridge deck and beams will be replaced.  The bridge will be slightly widened to meet current shoulder and lane width standards.

Construction Details


  • Design Firm: DLZ Indiana
  • Inspection Firm: Hamilton Co. Highway Dept.
  • Contractor: Hoosier Pride Excavating
  • Construction Start Date: May 2, 2022
  • Construction Completion: September 30, 2022
  • Construction Cost: $1.6 million
Funding
Design and construction costs will be funded locally.