106th St. & Mollenkopf Rd. Intersection Improvement

Project Information


Current Status


9/11/2020: Construction is complete.  

Project Location

The project will take place at the intersection of 106th St. and Mollenkopf Rd. in Fall Creek Township.

Google_StreetView
Opens a New Window.
close carousel
close carousel
close carousel

Project Scope


Intersection Improvements will consist of adding a left turn lane for westbound traffic and replacing the signal.

Reason for Project
Improvements are needed to improve traffic flow and reduce congestion.

Construction Details


  • Design Firm: A&F Engineering
  • Contractor: E&B Paving
  • Construction Start Date: July 7, 2020
  • Construction Completion: August 20, 2020
  • Construction Cost: TBD

Funding


Design costs will be locally funded. Construction will be funded 80% by Federal Aid / 20% local match.