106th St. & Mollenkopf Rd. Intersection Improvement

Project Information


Current Status


7/2/2020: On Tuesday July 7th, construction will begin. Traffic will be maintained on 106th St. and Mollenkopf Rd.  Please watch the area for lane restrictions.

Construction is expected to be complete on or before August 20, 2020.

Project Location


The project will take place at the intersection of 106th St. and Mollenkopf Rd. in Fall Creek Township.

Google_StreetView
Opens a New Window.
close carousel
close carousel

Project Scope


Intersection Improvements will consist of adding a left turn lane for westbound traffic and replacing the signal.

Reason for Project
Improvements are needed to improve traffic flow and reduce congestion.

Construction Details


  • Design Firm: A&F Engineering
  • Contractor: E&B Paving
  • Construction Start Date: July 7, 2020
  • Construction Completion: August 20, 2020
  • Construction Cost: TBD

Funding


Design costs will be locally funded. Construction will be funded 80% by Federal Aid / 20% local match.