Allisonville Rd. & 146th St. Interchange
Project Information
Current Status
5/31/22: Final design is underway. A public information meeting was held on February 9th regarding this project.
Project Location
Intersection of Allisonville Rd. and 146th St.
Reason for Project
This project is needed in order to reduce congestion at the existing intersection.
Project Scope
The existing intersection will be converted into a grade-separated interchange. Scoping for the interchange type is currently in process.
Construction Details
- Design Firm: United Consulting
- Inspection Firm: TBD
- Contractor: TBD
- Construction Start Date: Spring 2023
- Construction Completion: Fall 2024
- Construction Cost: $29 Million est.
Funding
Design costs will be funded locally. This project has been awarded $9.5M in federal funds for construction ($4.25M in CMAQ & $4.25M in STBG). The balance of construction costs will be funded locally.
Design costs will be funded locally. This project has been awarded $9.5M in federal funds for construction ($4.25M in CMAQ & $4.25M in STBG). The balance of construction costs will be funded locally.
-
Highway Department
1700 S 10th Street
Noblesville, IN 46060
email the Highway
317-773-7770
317-776-9814
After-Hours Emergency:
317-773-1282
Office Hours
Monday - Friday
8:00am - 4:30pm
Closed Holidays
Staff Directory